South Bonnyview and Bechelli Lane roundabout update


The City of Redding hopes to complete work on a roundabout project at Bechelli Lane and South Bonnyview by mid-August. (City of Redding)
The City of Redding hopes to complete work on a roundabout project at Bechelli Lane and South Bonnyview by mid-August. (City of Redding)
Facebook Share IconTwitter Share IconEmail Share Icon

The City of Redding is making progress on its roundabout project at South Bonnyview and Bechelli Lane and they hope to have the project completed by the middle of August.

They updated their Facebook page with information on the timeline of their projects, and what is to come next as the project progresses.

According to The City of Redding, this week they are expecting:

  • By Sunday, August 7, the paving for their roundabout is to be complete as well as temporary striping to be in place in the final configuration of the roundabout.
  • They expect the final striping for the project to be complete by the end of the following week.
  • Street lighting has not been started yet but is scheduled for installation in mid-August.

If you want more information or have questions regarding this project you can visit the city's website.